Insulation and Sheetrock
Back to
Project History 2006
Johnson Drywall blew in the cellulose insulation on February 18th, 2006.
This was an interesting process. Cellulose insulation is a higher quality
insulator than bat insulation. Johnson Drywall blew in the 12" lid, roof,
with an R value of 44, while cellulose in the 2" X 6" wall will provide an R-21
value. The cabin should be cozy and comfortable both winter and summer.
Johnson Drywall installed cellulose insulation February 18th, 2006. The equipment to blow in the insulation was very interesting. The crew did a amazing job. Johnson Drywall installed the insulation February 18th, 2006. On February 24, 2006 the cabin was ready for sheetrock. Cellulose insulation on the south Great Room wall. Jerry started the sheetrock project March 4th, 2006. The sheetrock make the cabin really take shape.
Johnson Drywall installed cellulose insulation February 18th, 2006.