Foundation and Footings
Back to
Project
History 2005
Matt and I started setting the foundation footings June 20,
2005. Matt had milled the forms with his saw mill. They were 2" X 9
1/2". The footing and rebar was finished June 22, 2005. The
footings averaged 9" deep by 18" and we used 8 yards of concrete
with 6 bag mix. The stem wall is 48" with horizontal #4 rebar at 36"
on-centers with 3 vertical rebar in the stem wall.
June 20, 2005. Ready to set the foundation forms. Form materials were 2" x 9 1/2" timber stock from Matt saw mill. The center bearing post footing was 14" deep by 24" X 24" box. Two runs of #4 rebar was set and tied 3 1/2" from the bottom of the foundation. The corners were over lapped. The center bearing post footing rebar was crisscrossed below the main two runs of rebar. Corner rebar configuration. June 23, 2005. Matt and I finished the setting the rebar. Matt, Allen, and Forest working of the foundation concert delivered June 28, 2005. Foundation forms. July 3, 2005. A 6" 200 schedule pipe was placed in the stem wall for the ABS drain pipe. The concert crew, Matt, Alan, Craig, Perry, Kodi, and Ina. After pulling the forms, we used a three inches sand bed in the bottom of the four foot crwal space. Installed 2" foam insulation and built the center pony wall. TJI's were used for the main floor joist.
June 20, 2005. Ready to set the foundation forms.