Project History 2005

Back to Project History

The Cabin project finally came to be.  Perry finalized all the requirement for the construction loan with Idaho Banking, setup the contract with Matt to be the General Contractor, completed the final plans with material lists.

Construction Events:

June 06, 2005

Excavation

 

August 13, 2005

Post and Beam

June 10, 2005

Crawl Space Excavation

 

August 24, 2005

Rafters

June 12, 2005

Water and Power Lines

Oct 24, 2005

Roofing

June 23, 2005

Foundation and Footings

 

Oct 25, 2005

Porches

July 27, 2005

Wall Construction

 

Nov 25,2005

Closed In - Metal Roof

August 8, 2005

Septic System - Backfill

 

   
         

Go to Project History 2006

 

Ray delivered the tractor that he rebuilt.

The tractor is a 1953 40 horse and Ray did a wonderful job in the complete rebuilt.

The tractor has a loader and box scraper.

Perry and Ray started removing the top soil May 1, 2005.

The cabin excavation site will be a big part of the project.

Ray and I started the excavation with Chuck's and Ray's tractors.

Ray digging the top soil May 2, 2005.

The pile of top soil May 2, 2005.

Ray diggin the top sole May 2, 2005.

May 5, 2005.

The rains came May 6th. The excavation had to halt for better weather.

 

Back to top