|
| |
Project History 2005
Back to Project History
The Cabin project finally came to be.
Perry finalized all the requirement for the construction loan with Idaho
Banking, setup the contract with Matt to be the General Contractor, completed
the final plans with material lists.
Construction Events:
|
June 06, 2005 |
Excavation |
|
August 13, 2005 |
Post and Beam |
|
June 10, 2005 |
Crawl Space Excavation |
|
August 24, 2005 |
Rafters |
|
June 12, 2005 |
Water and Power Lines |
|
Oct 24, 2005 |
Roofing |
|
June 23, 2005 |
Foundation and Footings |
|
Oct 25, 2005 |
Porches |
|
July 27, 2005 |
Wall Construction |
|
Nov 25,2005 |
Closed In - Metal Roof |
|
August 8, 2005 |
Septic System - Backfill |
|
|
|
|
|
|
|
|
|
|
Go to Project History 2006 |
Ray delivered the tractor that he rebuilt. The tractor is a 1953 40 horse and Ray did a wonderful job in the complete rebuilt. The tractor has a loader and box scraper. Perry and Ray started removing the top soil May 1, 2005. The cabin excavation site will be a big part of the project. Ray and I started the excavation with Chuck's and Ray's tractors. Ray digging the top soil May 2, 2005. The pile of top soil May 2, 2005. Ray diggin the top sole May 2, 2005. The rains came May 6th. The excavation had to halt for better weather.
Ray delivered the tractor that he rebuilt.
Back to top
|