|
| | Project History 2001
Back
to Project History
Thanks to many friends, we were able to set the trusses, lay the sheathing
and roofing paper. The metal roof project was contracted. Then we
started the siding project.

We started working on the shop early in the spring. Everything was ready to do the siding and roof. Northeast end of the building. We finished to stairs to the upper room. The flooring was finished. Kodi and Kris did more work on the fire pit. We had the medal roof contracted. West side of the building. West side of the building. Back storage area with the wooden doors that Perry built to the wood shed. Roofing finished on the storage area. Perry finished placing more shop equipment in the shop. Perry built the workbench for the large wood vices. The shop did not have insulation as yet The vacuum system was up and running. The next project was the out feed table for the table saw. Out feed table for the table saw. The out feed table held routers and sanding equipment. The siding project started. East side of the building. West side of the building.
We started working on the shop early in the spring.
Back to Top
|